Old Blackwater Pool Precinct Redevelopment Project
Share Old Blackwater Pool Precinct Redevelopment Project on FacebookShare Old Blackwater Pool Precinct Redevelopment Project on TwitterShare Old Blackwater Pool Precinct Redevelopment Project on LinkedinEmail Old Blackwater Pool Precinct Redevelopment Project link
This stage of consultation has concluded.
Central Highlands Regional Council is in the early stages of planning for the redevelopment of Blackwater's old Aquatic Centre in MacKenzie Street, Blackwater.
This project is part of the Blackwater old Aquatic Centre Master Plan development to re-design the space encompassing the old aquatic centre, council offices, library, Lions Park and adjacent open space.
In November 2018, community members were invited to provide feedback on a draft conceptual plan and what should be included to meet community need and recognise historical or cultural significance.
An engagement was also conducted separately on the proposed new Blackwater library facility.
All feedback received was considered in a draft masterplan presented to council in November 2019. In July 2020, the masterplan was endorsed for delivery over multiple stages, commencing in the 2020-2021 financial year.
Central Highlands Regional Council is in the early stages of planning for the redevelopment of Blackwater's old Aquatic Centre in MacKenzie Street, Blackwater.
This project is part of the Blackwater old Aquatic Centre Master Plan development to re-design the space encompassing the old aquatic centre, council offices, library, Lions Park and adjacent open space.
In November 2018, community members were invited to provide feedback on a draft conceptual plan and what should be included to meet community need and recognise historical or cultural significance.
An engagement was also conducted separately on the proposed new Blackwater library facility.
All feedback received was considered in a draft masterplan presented to council in November 2019. In July 2020, the masterplan was endorsed for delivery over multiple stages, commencing in the 2020-2021 financial year.
If you have feedback about this consultation, please share your comments below.
This stage of consultation has concluded.
Share Feedback on FacebookShare Feedback on TwitterShare Feedback on LinkedinEmail Feedback link
Project stages
Engagement on concept plan
Old Blackwater Pool Precinct Redevelopment Project has finished this stage
13 November - 19 December 2018
Survey (print and online)
24 November 2018- Consultation with Ghungalu Elders at the site
Information booth & feedback opportunity
Old Blackwater Pool Precinct Redevelopment Project has finished this stage
Location: Blackwater Town Centre
6 December 2018
10.00am - 4.00pm
Blackwater Library Survey
Old Blackwater Pool Precinct Redevelopment Project has finished this stage
5 April - 5.00pm 3 May 2019
Information sessions
@ Blackwater Town Centre
Monday 15 April 2019
6.30pm - 7.15pm
Tuesday 16 April 2019
11.00am - 11.45am
Councillor workshop
Old Blackwater Pool Precinct Redevelopment Project has finished this stage
25 June 2019 - Councillors attended a workshop on feasibility of the library component.
Draft Masterplan
Old Blackwater Pool Precinct Redevelopment Project has finished this stage
November 2019 - Draft masterplan presented to council
Masterplan endorsed at General Council Meeting
Old Blackwater Pool Precinct Redevelopment Project has finished this stage
22 July 2020
Next steps
Old Blackwater Pool Precinct Redevelopment Project is currently at this stage
Delivery of the Blackwater Old Pool Precinct Masterplan will take place over multiple stages, commencing in the 2020-2021 financial year. To find out about opportunities to provide further input, register for the Have Your Say website.